NextGenAccess completes Ultrafast Surrey build

1st May 2017

Fibre deployment

NextGenAccess has completed the 1st phase of its Ultrafast Surrey Build by completing the main fibre stretch between Guildford exchange and Godalming, which is a 9km system. The system fibre has been fully tested and running electronics supporting end services up to 10GB, with multiple fibre pairs installed to increase the multiple 10GB backhaul from Guildford and Godalming ends of the system as required. The full deployment of 1GB Ultrafast services will start after Sales and Marketing effort and website upgrade in July 2017.